Glatfelter Ft. Smith is an existing 200,000 sq. ft. Mitsubishi building located at Chaffee Crossing. The existing building is being retrofitted by Glatfelter to meet their needs. Glatfelter is a domestic and international paper manufacture. The Fort Smith plant will create 83 high-skilled jobs. Action is under contract for $5.4 million.

General Contractor: Glatfelter
Architect/Engineers: Cromwell
Project Start Date: 12-22-2016
Project End Date: 12-1-2017

Systems Include:

  • Condensing Water
  • Process Chill Water
  • Heating Water
  • RO Water
  • Process Water
  • Domestic Water
  • Sanitary Sewer
  • Condensate Piping
  • Natural Gas & Compressed Air

Subcontractors:

  • Concrete
  • SSI, Insulation
  • Pro Insulation, Steel/Crane
  • Holmes Erecting, Utilities
  • AJ Greenwood, Core Drilling
  • Any Concrete Cutting, Excavation
  • Hightower Construction & Duct
  • ECS